Speed
Using a ‘cast on-site’ method at ground level allows the trades to start work on a finished slab. This minimizes logistical issues and allows the building envelope to be erected earlier thus reducing the total construction time.
Video:
- Time-lapse of school addition. (2:44)
Chronology
The pictures below show the chronology of construction of a two storey, 52,000 sq.ft. school in 5 1/2 months using the SiteCast™ building system:
 |
 |
March
Foundations, foundation insulation, weeping tile and underground electrical and plumbing services were installed.
|
 |
April
Floor slab cast to a "super flat" finish. Fabrication of Tilt-Up panels begins. Site services proceeded with installation of water main.
|
 |
May
Panel fabrication continued. Panel and structural steel installation started. Installation of hydro duct bank and transformer and start of mechanical and electrical trades.
|
 |
June
Completion of steel roof deck allowed roofing to start. Sealing of the building proceeded with the installation of window frames and glazing. Fire spray contractor begins. Electrical, mechanical, ductwork and sprinkler trades made rapid progress.
|
 |
July
Electrical and mechanical rough-ins completed. Interior finishings started. Exterior hard landscaping started.
|
 |
August
Occupancy took place on August 16th. Detail interior finishings completed and exterior landscape completed.
|
|
|
|
|